How long does it take for a cleanroom cabin to be ready for use?

TL;DR

The total time consists of the delivery time and the actual assembly. Due to the modular aluminum construction, an average cleanroom cabin is on-site within 2 to 5 days fully built. Since there are no construction chemical drying times, the ISO class can be validated immediately after final assembly.

Nordair Systems (Modular)
Classic Cleanroom (Drywall)
Assembly Principle
Mechanical fastening
Filling, sanding, painting
Site Duration
2 – 5 days
3 – 6 weeks
Electrical
Plug & Play (Connectors)
Complex point-to-point wiring on-site
Production Start
Immediate post-assembly
Delayed by outgassing/cleaning

Drywall vs. curing time

The time to operational readiness (“time-to-production”) at Nordair Systems is drastically shorter than in traditional plant engineering, as we rely on physical dry assembly Set. A conventional cleanroom cabin made of plasterboard or mortared elements requires chemical curing times. An aluminum-based Nordair system is bolted together. There are no “wet” processes. A team of two fitters is constructing a 50 m² cabin purely mechanically in 2 to 4 working days.

Plug & Play from Nordair Systems

The most common bottleneck during installation is not the scaffolding, but the wiring. To eliminate electrician hours, our filter fan units (FFUs) and LED panels use a standardized Cold device plug logic. The components are inserted into the ceiling and immediately connected to the prepared electrical network. No complex PLC programming is required on site.